DENVER — Denver International Airport may have to add 10 months to its projected 3-year renovation project. A new monthly report from the contracting team showed some of the concrete samples from the airport’s terminal floor tested weaker than expected.

 

Great Hall Partner’s forecasted delay is 209 business days. The original completion date was Nov. 3, 2021. The new estimate is Aug. 30, 2022, according to the December report released last week.

 