Three senior executives at the company leading the £9 billion regeneration of Battersea Power Station have quit, the Evening Standard has learned.

 

Chief operating officer Simon Jenner and head of delivery Matt Lusty resigned from the Malaysia-owned Battersea Power Station Development Company (BPSDC) last week.

 

Last month Kevin Bundy, leading work on the Grade II*-listed building itself as head of Phase Two, said he was leaving the company.

https://www.standard.co.uk/news/london/battersea-power-station-project-loses-three-top-executives-a4089191.html

 

Battersea power station home buyers rip up contracts

Regeneration project is running so late that clients are able to walk away

https://www.ft.com/content/d3f538ba-4bdf-11e9-bbc9-6917dce3dc62

Anonymous ID: 434b7c March 27, 2019, 8:20 p.m. No.5934911   🗄️.is 🔗kun   >>5011 >>5291 >>5653 >>5799

>>5934822

PNB, EPF completes Battersea Power Station’s commercial assets acquisition

Read more at https://www.thestar.com.my/business/business-news/2019/03/14/pnb-epf-completes-battersea-power-station-commercial-assets-acquisition/#vDulSYSw4eQbKpUy.99

 

https://www.thestar.com.my/business/business-news/2019/03/14/pnb-epf-completes-battersea-power-station-commercial-assets-acquisition/

Anonymous ID: 434b7c March 27, 2019, 8:31 p.m. No.5935096   🗄️.is 🔗kun

>>5934822

>>5934860

past comms?

The exact location of the 8.5km (5.3-mile) tunnel near the river must remain under wraps for “security reasons”. Its depth ranges from 72ft (22m) to 98ft (30m) depending on the location of old gas pipes, rail tracks and sewers criss-crossing around it.

 

The two-year project included digging a 108ft (330m) spur, known as the Battersea Cable Tunnel, that breaks into the existing main bore. The spur was drilled out using a tunnel-boring machine, which heaved concrete reinforcement panels into the clay as it went.

 

A junction chamber linking the spur to the main tunnel was dug by hand using techniques from the time of Victorian engineer Isambard Kingdom Brunel, but with modern pneumatic shovels.

 

Much of the digging was done while 132,000-volt cables were live in the existing main tunnel, which are about 500 times more dangerous than a domestic plug.

 

Rosie Bridger, project manager for UK Power Networks, said: “As London grows, demand continues to increase, and working in central London space is tight.

 

“One of the biggest challenges on this project is that we’ve got to maintain security of supply to our London customers.”

Anonymous ID: 434b7c March 27, 2019, 8:37 p.m. No.5935265   🗄️.is 🔗kun

>>5934822

Only three stacks ramain

 

Battersea is a relatively tight site that is jam-packed with more than 17 tower cranes. Our tour guide also said the whole development placed an enormous demand for concrete on a batching plant nearby, which was the busiest in Europe.

 

https://www.constructionnews.co.uk/projects/battersea-power-station-proves-a-towering-showcase/10041247.article

Anonymous ID: 434b7c March 27, 2019, 8:57 p.m. No.5935820   🗄️.is 🔗kun   >>5856

>>5935554

I was still on the Battersea Power station but since you brought it up Anon

https://www.whitehouse.gov/presidential-actions/executive-order-coordinating-national-resilience-electromagnetic-pulses/